Road Safety Plans for Edinburgh South West

On Thursday next week, Councillors will discuss Council road safety projects in Edinburgh. Demand for projects always exceeds the available budget – the table below is simply my summary of what’s planned for Edinburgh South West.

Scheme NameDetailsCommentExpected Cost
Dalmahoy JunctionJunction Improvement To be carried forward to 2026/27 This project is progressing well with land agreements finalised October 2025 and drainage options almost complete. Once these have been finalised the project will move to the final design stage and then construction.£1.7m 
Forrester High SchoolImprovements to crossing and footway facilitiesBeing delivered in conjunction with broader WEL project in 2025/26£1m
Slateford Road – between Hutchison  Crossway and Appin PlaceToucan crossing – carried forward from last yearTRO progress underway£115,000
Colinton Road – at Craiglockhart ParkHistorical – Non-signalisedProject brief currently being prepared, for delivery before April 2026£57,000
Dundee street at junction with Drysdale roadDundee Street At Junction With Drysdale RoadThis junction forms part of an Active Travel project with will deliver the improvements required. Removed from AIP delivery programme for 2025/26n/a
Morrison Street (B700) near junction with Lothian Road (A700)Morrison Street (B700) Near Junction With Lothian Road (A700)Following analysis of the AIP outputs, Officers deemed it appropriate to monitor the site rather than install measures. Junction will be added to the Safer Streets Prioritisation Process. Removed from AIP delivery programme for 2025/26.Unknown
Gorgie Road (A71) at junction with Chesser AvenueGorgie Road (A71) At Junction With Chesser AvenueFollowing analysis of the AIP outputs, Officers deemed it appropriate to monitor the site than install measures. Junction will be added to the Safer StreetsUnknown
Longstone PSPedestrians crossing on Kingsknowe Rd N and Duncan’s GaitDesign underway for delivery before April 2026£57,000
TynecastleZebra crossing at McLeod StreetDesign underway for delivery before April 2026£57,000
Ashley TerraceTwo crossings on Ashley Terrace and footway buildout on Cowan RoadRe-design underway following feedback from the school – delivery before April 2026£115,000
Longstone PSImproved markings to highlight pedestrian crossing drive at entrance to drive (red chips)Design underway for delivery before April 2026£2,300
Nether Currie Repaint Existing Road Markings. Install Warning Signs. Install Pedestrian Guard Rail (PGR)Design underway for delivery before April 2026£2,300
Longstone PSParking restrictionsTRO progress underway for delivery 2026/27£575
Currie PrimaryParking restrictionsTRO progress underway for delivery 2026/27£575
Currie HighParking restrictionsTRO progress underway for delivery 2026/27£575